Prijepolje Fire Destroys Trenteks Factory Warehouse
The blaze broke out just after 2 a.m. in Kolovrat and no one was injured. Management says the warehouse is a total loss, but production will continue.

A fire in Prijepolje broke out on the night between Thursday, November 19, and Friday, November 20, 2026, shortly after 2 a.m., on the grounds of the Trenteks textile factory in the Kolovrat district. A warehouse burned down, and no one was injured.
Firefighting and rescue crews contained the blaze after several hours and kept it from spreading to the other halls in the complex. It has not been reported how many firefighters and vehicles were deployed. Thick smoke covered Kolovrat and the surrounding area through the night and into the morning.
What exactly burned in Kolovrat?
Sources disagree. RTS, as reported by Danas and Borba, said in its morning news that, according to unofficial information, one of the production buildings was hit. Sandzak Live and Telegraf report that a raw materials warehouse burned.
The accounts also differ on who used the warehouse. Sandzak Live writes that it was a former weaving mill that the company Prispin leased two years ago and used to store large quantities of raw materials. Telegraf, citing a source at the scene, says the warehouse had been rented to an Italian company for storing raw materials.
Media spell the factory’s name four ways: Trenteks, Trendeks, Trendtex and Trendex. This article uses the form given by the source who spoke with management.
According to Sandzak Live, the fire was first noticed by security staff, among them a guard from the neighboring company Jela, and they called the firefighters. According to the Prijepolje firefighting and rescue unit, as reported by Danas and Borba, the fire was contained in the early morning hours but had not been fully put out.
How big is the damage, and what was saved?
Trenteks director Suanita Celebic said there were no employees in the warehouse when the fire started, so no one was hurt. According to management’s first estimate, the damage to the affected building is total. The final figure will be known only after the competent authorities complete their on-site investigation.
The new spinning mill where Prispin operates and Trenteks’ production plants were spared.
Prispin director Sasa Danojlic said production will continue, that new raw materials have already been ordered and that minor delays are expected. He stressed that the most important thing is that no one was killed, and left the determination of the cause to the competent authorities.
What caused the fire?
The cause has not been established. Celebic said the power cut out during the night and that the fire started after electricity was restored. It has not been confirmed whether the two events are connected.
Faulty electrical wiring has been mentioned as a possible cause, but there is no official finding. The on-site investigation and checks by the competent authorities are expected to show what happened.
Parts of the burned site could smolder for about two more days, because the warehouse held polyester and acrylic materials.
This is not the company’s first fire
Sandzak Danas recalls that a fire already struck the company on June 23, 2018, destroying a raw materials warehouse and a garment production unit of about 400 square meters. Ten firefighters from two crews put out the blaze at the time. The same paper says there is no basis for linking the two events, and it is not known whether their causes were similar.