HIP Petrohemija Completes 15 Million Euro Overhaul

The Pancevo plants were shut down for about two months, with more than 1,100 people working on the overhaul. Restarting the ethylene plant takes about 48 hours.

Branko Petrović2 min read0
Podeli
Industrial plant of Petrohemija in Pancevo
Petrohemija in Pancevo, file photo accompanying news of the completed overhaul/ Photo: N1 info / AFP

An overhaul worth about 15 million euros has been completed at HIP Petrohemija in Pancevo, the company said on November 23, 2026. The plants were shut down for about two months during the work, and production restarts with the ethylene plant.

What was done in Petrohemija’s largest overhaul

The company calls this the largest overhaul in its history. More than 11,000 activities were carried out, and over 1,100 people worked on the project: about 700 outside contractors and about 400 Petrohemija employees.

According to the company’s statement, the most important completed works include:

  • an overhaul of two high-pressure steam boilers at the ethylene plant
  • reconstruction of the steel structure in the finishing building of the synthetic rubber plant in Elemir
  • work required by law, including inspection and cleaning of equipment

The company expects the overhaul to bring steadier plant operation, better energy efficiency and improved production processes.

What the Petrohemija director says

In the company’s statement, director Goran Stojilkovic thanked employees and contractors, and tied the result to safety and environmental protection:

“This result was achieved thanks to the great dedication of our employees and contractors, with strict observance of the highest standards of safety and environmental protection.”

Stojilkovic also stressed that the work on the equipment matters beyond the company itself:

“By modernizing key equipment, we have further strengthened the reliability of Petrohemija, which is of strategic importance not only for our company, but for the entire NIS refining complex.”

What can residents notice when the plant restarts?

When the ethylene plant starts up, louder noise, smoke and occasional flaring at the flare stack are possible. The company says these effects are expected from November 23 and should last about 48 hours. The restart follows an established schedule and company procedures, as stated, with the prescribed environmental standards observed.

The synthetic rubber plant in Elemir is due to resume work on December 8, about fifteen days after the ethylene plant.

Why Petrohemija matters for the NIS complex

Petrohemija is part of the refining complex of Naftna Industrija Srbije (NIS) and is technologically linked to the Pancevo oil refinery. Because of that link, the company describes the overhaul as important for the whole complex, not just for its own plants.

We earlier reported that JANAF is releasing oil to NIS again after a 14-day interruption. The Petrohemija statement, in the parts carried by the media, does not mention that event, so it cannot be said that the two stories are linked. The only thing that is certain is the order the company itself announced: the ethylene plant starts on November 23, and the rubber plant in Elemir two weeks later.

Podeli
Komentari…
Next storyHormuz Tension Reaches Pancevo as NIS Faces July 31 DeadlineThe closure of the Strait of Hormuz threatens crude deliveries to the Pancevo refinery just as the OFAC licence expires and MOL finalises talks with ADNOK over taking control of NIS.

From other sections

Most read today

  1. European Parliament debates Vukovar resolution on Monday
  2. Brnabic posts threat to her child, blames students, media
  3. SNS Appeals to Council of Europe, OSCE on Vice Presidents
  4. Milivojevic Demands SNS Ban and a Belgrade Trial
  5. Igor Dodik named to form new Republika Srpska government

Komentari (0)

Ostavi komentar

Komentari prolaze kratku moderaciju. Lični napadi i govor mržnje se brišu.

Još nema komentara. Budi prvi i podeli mišljenje.