HIP Petrohemija Completes 15 Million Euro Overhaul
The Pancevo plants were shut down for about two months, with more than 1,100 people working on the overhaul. Restarting the ethylene plant takes about 48 hours.

An overhaul worth about 15 million euros has been completed at HIP Petrohemija in Pancevo, the company said on November 23, 2026. The plants were shut down for about two months during the work, and production restarts with the ethylene plant.
What was done in Petrohemija’s largest overhaul
The company calls this the largest overhaul in its history. More than 11,000 activities were carried out, and over 1,100 people worked on the project: about 700 outside contractors and about 400 Petrohemija employees.
According to the company’s statement, the most important completed works include:
- an overhaul of two high-pressure steam boilers at the ethylene plant
- reconstruction of the steel structure in the finishing building of the synthetic rubber plant in Elemir
- work required by law, including inspection and cleaning of equipment
The company expects the overhaul to bring steadier plant operation, better energy efficiency and improved production processes.
What the Petrohemija director says
In the company’s statement, director Goran Stojilkovic thanked employees and contractors, and tied the result to safety and environmental protection:
“This result was achieved thanks to the great dedication of our employees and contractors, with strict observance of the highest standards of safety and environmental protection.”
Stojilkovic also stressed that the work on the equipment matters beyond the company itself:
“By modernizing key equipment, we have further strengthened the reliability of Petrohemija, which is of strategic importance not only for our company, but for the entire NIS refining complex.”
What can residents notice when the plant restarts?
When the ethylene plant starts up, louder noise, smoke and occasional flaring at the flare stack are possible. The company says these effects are expected from November 23 and should last about 48 hours. The restart follows an established schedule and company procedures, as stated, with the prescribed environmental standards observed.
The synthetic rubber plant in Elemir is due to resume work on December 8, about fifteen days after the ethylene plant.
Why Petrohemija matters for the NIS complex
Petrohemija is part of the refining complex of Naftna Industrija Srbije (NIS) and is technologically linked to the Pancevo oil refinery. Because of that link, the company describes the overhaul as important for the whole complex, not just for its own plants.
We earlier reported that JANAF is releasing oil to NIS again after a 14-day interruption. The Petrohemija statement, in the parts carried by the media, does not mention that event, so it cannot be said that the two stories are linked. The only thing that is certain is the order the company itself announced: the ethylene plant starts on November 23, and the rubber plant in Elemir two weeks later.