Budva Bypass: Preparatory Works Start October 5
Montenegro's government approved preparatory works on the Markovici-Lastva Grbaljska section, a 237.47 million euro project, with a ceremony set for Monday at 12:30.

For Serbian drivers who spend the summer on the Montenegrin coast, the Budva bypass is a project measured in the very summer queues that justify building it. The first phase of this expressway gets its formal start on Monday, October 5: a ceremony marking the beginning of preparatory works is scheduled for 12:30 in Lastva Grbaljska, and according to RTCG it will be attended by representatives of the Montenegrin government, state institutions, international partners and the contractors.
What is being built, and how much does the Budva bypass cost?
The project covers the section between the Markovici and Lastva Grbaljska interchanges, about eight kilometers long, or about nine counting the access road. The design-and-build contract is worth 237.47 million euros including value added tax, the money comes from the capital budget, and the construction deadline is four years. Investitor.me, citing an earlier announcement by the state company Monteput, specifies that the 48 months are counted from the moment the contractor is introduced to the site, not from the signing of the contract or the government’s decision.
The route is technically demanding. According to Monteput, roughly 70 percent of the section consists of structures, including about 4.3 kilometers of tunnels and 1.4 kilometers of bridges and viaducts. Prime Minister Milojko Spajic spoke of a larger figure when the contract was signed, and Dan quotes him this way:
The road from Markovici to Lastva Grbaljska, those eight or nine kilometers, will be built on very demanding terrain, with as many as six kilometers of bridges and tunnels
Spajic thus spoke of six kilometers of bridges and tunnels, while Monteput’s figures add up to 5.7 (4.3 plus 1.4), and the sources do not explain the gap. The new link is meant to connect the Podgorica-Budva and Budva-Tivat main roads, so that transit traffic bypasses the city’s urban core.
Who won the contract?
The contract was signed on June 29 with a consortium made up of Briv Construction, Herc gradnja, Hering, IPSA Institut and Shandong Foreign Economic & Technical Cooperation. It was signed by Monteput’s general manager Milan Ljiljanic and the director of Briv Construction, Milan Maric. The model is “design and build,” meaning the same consortium prepares the project documentation and carries out the works, and the first year is set aside for the main design, the necessary approvals and preparatory works.
Expert supervision of design and construction went to the Construction Institute, Central Road Laboratory, with which Monteput signed a contract in early July.
What are preparatory works, and why did the government have to approve them?
On September 17, Monteput asked the Ministry of Spatial Planning, Urban Planning and State Property to grant its consent, and the government approved it at the end of September. Dan reports that preparatory works on facilities of general interest can be carried out before a building permit under Article 38 of the Law on Construction of Buildings, provided the investor has secured the required proof and proof that the construction is acceptable in terms of environmental impact. A decision of consent from the Environmental Protection Agency has also been obtained.
Preparatory works include:
- fencing and marking the construction site
- clearing the terrain and removing vegetation
- access roads and auxiliary roads
- work platforms, site settlements, camps and offices
- temporary electricity and water connections
Monteput will submit the application for a building permit for the road itself later, so this is a step toward setting up the site, not the start of the main construction works.
How much does the state pay on top of the contract?
The contracted value is not the total cost. In June, Ljiljanic said that expropriation is under way and will cost the state an additional 18 million euros or so. Public interest in expropriation has been established for properties in the cadastral municipalities of Prijeradi, Gorovici and Lastva in the Kotor territory, as well as Maine in the Budva territory.
Finance Minister Novica Vukovic said at the time that the project would be financed from the capital budget, and Spajic stated that the financial structure is secured.
What comes after the first phase?
The second phase is a separate tender for the electromechanical part: equipment and installations in the tunnels, the power grid, water pipes and pumps, control and monitoring systems, traffic signaling, and equipment for the control center and maintenance base. The first phase covers design and construction, and a tender for the second will be announced, RTCG reports.
There is also a discrepancy in the sources ahead of the ceremony. Dan, citing unofficial information from the newspaper Pobjeda, wrote that works would begin in early October, while Investitor.me, in a text from September 24, notes that the government’s information did not give a precise date for the contractor to move onto the site. The October 5 date comes from RTCG’s announcement.