DPM Metals: Coka Rakita decisions may await new government
In its third-quarter report, the Canadian firm says decisions on the gold mine project near Zagubica may wait for a new government. It is raising exploration spending in Serbia to $38 to 40 million.

Canada’s DPM Metals Inc. (formerly Dundee Precious Metals) said in its third-quarter 2026 report that administrative and regulatory deadlines for decisions on the Coka Rakita project near Zagubica could be extended until a new government is formed and the National Assembly is constituted after the October 25 parliamentary elections. News of the report came out on November 17, the day of the Assembly’s constitutive session.
Coka Rakita is a planned gold mine in eastern Serbia. The company has been present in the country since 2004, and in the same document it raises its exploration budget for its Serbian licenses.
What does the company say about the deadlines?
DPM Metals does not announce a halt, only the possibility of a delay. The company says it will align the timing of the next project phase with the relevant Serbian authorities if government formation requires it, while engineering and procurement continue.
Technical preparations include dismantling and refurbishing parts of the processing plant from the Ada Tepe mine in Bulgaria, where production ended on July 15, 2026. The company is also speeding up procurement and locking in manufacturing slots for the most critical equipment, selecting contractors for underground work and advancing detailed engineering.
How much money is tied to Coka Rakita?
Growth capital spending on the project for 2026 is planned at $49 to 53 million. In the first nine months, $13.7 million was spent. This year’s guidance also includes about $42 million in pre-committed early capital for engaging contractors and ordering equipment before a formal construction decision, an amount that depends on progress with permits.
According to the company’s guidance, part of that money may be spent before a construction decision is made, but only if permitting moves forward.
Exploration: from $25 to 30 million up to $38 to 40 million
The annual exploration budget in Serbia for 2026 has been raised to $38 to 40 million, from the original $25 to 30 million. By the end of September, $29.5 million had been spent.
In the third quarter, a total of 19,283 meters were drilled across the Potaj Cuka, Coka Rakita, Pester Jug and Umka licenses. At Coka Rakita, up to 15 drill rigs completed 12,762 meters, and at Potaj Cuka, at the Valja Saka site, 3,558 meters.
Drilling at Dumitru Potok and Rakita Sever shows mineralization extending to the west, southwest and north, which the report says suggests the tonnage of mineralized material could be larger than previously estimated. As a result, the 2026 drilling program has been expanded by a further 12,000 to 15,000 meters.
The company’s president and chief executive, David Rae, described the timeline for the next step this way:
“In the Rakita camp, we are advancing the Dumitru Potok project toward an updated mineral resource estimate in the first quarter of 2027 and a preliminary economic assessment by the end of 2027.”
In other words, an updated mineral resource estimate for Dumitru Potok is expected in the first quarter of 2027, with a preliminary economic assessment by the end of that year.
How did the company do overall?
Company-wide, DPM Metals posted third-quarter revenue of $311.6 million, up 17% from a year earlier, and net income of $133.8 million. Production came to 95,917 ounces of gold equivalent, nearly three tonnes.
The quarter ended with $839.2 million in cash and no debt. The dividend is $0.04 per share, payable on January 15, 2027. For the first nine months, the company also booked $2.65 million from the sale of assets and data for an exploration license in Serbia that it no longer holds.