Nis Gas Power Plant: EPS and SOCAR Sign Agreement
EPS and Srbijagas hold 50 percent of the joint company, Azerbaijan's SOCAR the other 50. The 500 MW plant is due to be completed by 2030.

A 500-megawatt gas power plant in Nis is supposed to be built within the next four years, by 2030, and the shareholder agreement for its development was signed on September 30 at the Serbian Government. The agreement was signed by Elektroprivreda Srbije (EPS), Srbijagas and Azerbaijan’s state oil company SOCAR, and it starts the process of setting up a joint company, the Ministry of Mining and Energy said in a statement.
The statement does not give the value of the investment. What is known is who will hold what share of the future company, what has been done so far and what comes before an investment decision is made.
Who signed the agreement
EPS was represented by its chief executive Dusan Zivkovic, Srbijagas by its chief executive Dusan Bajatovic, and SOCAR by Elchin Ibadov, adviser to the company’s president for development and portfolio and director of SOCAR Turkey. The signing was attended by Dubravka Djedovic Handanovic, the caretaker Minister of Mining and Energy, and Azerbaijan’s ambassador to Serbia, Tahir Tagizade.
Before the signing, the project’s Steering Committee held its first meeting to discuss activities related to developing and delivering the plant. A management board, a project management team and five technical teams, one for each area of work, were formed earlier.
How will the joint company be divided?
Fifty percent of the joint company belongs to the Serbian companies, meaning EPS and Srbijagas together, and 50 percent to Azerbaijan’s SOCAR. The agreement defines the companies’ rights and obligations, joint management, unanimity on key decisions during the preparatory phase of the project, and the financing of development activities.
The plant is planned as a combined-cycle gas turbine facility with a capacity of 500 megawatts, producing both electricity and heat. It is the first joint project of EPS, Srbijagas and SOCAR.
What has been done on the project so far?
Zivkovic said that the Pre-Feasibility Study has been completed, that the Spatial Plan of the City of Nis has been adopted, that the planning documentation and a study on connecting to the transmission system have been commissioned, that a designer has been hired, and that work has begun on the Feasibility Study and technical documentation. The minister added that a technical feasibility study has also been commissioned, and that she expects all analyses to be finished by February or March next year. On that basis the economic feasibility study is to be completed and talks are to begin with the lenders who will finance the project.
Zivkovic explained why EPS is joining the project:
“In a time of energy transition and ever greater and more intense global challenges, new energy, new megawatts, is an imperative. EPS is determined to ensure energy security and diversify its sources and to use gas as a transitional fuel. We have been working actively on the project for months with a clear goal of building a highly efficient combined-cycle gas plant with a capacity of 500 MW”
In the same address he added that the project is part of a broader shift in the company’s direction: “Yes, this is a process of diversification, as well as decarbonization, but it is also an important process for the business development of Elektroprivreda Srbije as a company,” Zivkovic said.
Why gas, and why Nis?
Djedovic Handanovic tied the project to electricity consumption and the structure of generation. She said Serbia needs more and more electricity, base-load power in particular, because it still relies predominantly on coal, and that hydrology this year was very poor, which is why new reliable sources of base-load energy are needed. She described the energy partnership with Azerbaijan this way:
“This is a good basis for developing a project of long-term importance for Serbia, above all because of growing electricity consumption and the need for cleaner energy sources, and gas is that compared with coal and fuel oil and represents a transitional fuel in the process of energy transition”
According to her, setting up the joint company, the next step after the signing, will allow more efficient preparation of a plant that is, in her words, “very important for electricity production, balancing the system and attracting investment in the south of Serbia”.
Bajatovic said Serbia already has a strategic gas partner in Azerbaijan:
“After Russia, Azerbaijan is Serbia’s largest supplier of natural gas, and it is logical that we are building a strategic partnership with Azerbaijan in terms of building a gas power plant as well. I am glad we are making progress on this project. A lot has already been done, so I have no doubt that we will build a new gas power plant”
He also pointed out that EPS needs the plant above all to balance the power system. The minister recalled that SOCAR has supplied Serbia with gas for the past three years, since the gas interconnector with Bulgaria was completed, and that it will continue to do so this winter.
From the February agreement to the shareholder agreement
The shareholder agreement is not the first step. In February this year in Belgrade, Serbia and Azerbaijan signed an agreement on the development, design, construction and operation of a combined-cycle power plant, in the presence of Serbian President Aleksandar Vucic and Azerbaijani President Ilham Aliyev. The National Assembly ratified that agreement. Ibadov tied the signing of the shareholder agreement to it:
“Today’s signing is a very important step for Azerbaijan and continues from the Intergovernmental Agreement and reflects the friendship that our two countries have developed through the energy partnership. This agreement enables SOCAR and EPS to jointly develop a combined-cycle gas power plant in Nis”
According to Ibadov, the two countries will jointly prepare a technical feasibility study with a team of engineering experts. He also set out an intention: “The plan is to produce electricity for the Serbian grid and create new generation capacity for Serbia’s energy system. And we believe this will contribute to a more stable and reliable electricity supply and broader energy security of the country.”
What comes next
The next step is setting up the joint company, followed by technical and economic analyses and the feasibility study. The minister repeated the deadline for completing the plant:
“We have very good partners on this project and I think there are no obstacles to it being successful, but I say and demand that it also be delivered efficiently, with deadlines, so that by 2030 we have the project completed. Thank you all for the cooperation”
The decision to actually build the plant has not been made yet. Ibadov said: “When the preparatory work is completed, our goal is to reach a joint investment decision.” Until then, the shareholder agreement governs only the preparatory phase: who decides, how decisions are made and who pays for development activities.