Tirsova 2 Deadlines Differ From Source to Source
Vucic toured construction sites on Deligradska and Koste Todorovica streets, and figures on the size of Tirsova 2, its bed count and completion date vary depending on which source covered the visit.

Serbian President Aleksandar Vucic visited the construction site of the new Tirsova 2 university children’s clinic on Deligradska Street on August 18 at 10:30 a.m., half an hour after touring renovation work at the Clinic for Gynecology and Obstetrics on Koste Todorovica Street. New deadlines were announced at both sites that day, but the figures that reached the public did not match: the future building’s size, its bed count and the month the children’s clinic is expected to open all differ depending on the source.
Health Minister Zlatibor Loncar, Finance Minister Sinisa Mali, Minister for Public Investment Darko Glisic, Belgrade Mayor Aleksandar Sapic and University Children’s Clinic director Sinisa Ducic attended the visit.
At the Deligradska site, Vucic said Tirsova 2 is “a dream of generations” and announced that construction would be finished before the opening of Expo.
How big is Tirsova 2, and when will it open?
This is where the discrepancies start. Radio Television of Serbia (RTS), citing tender documentation, puts the complex’s total floor area at 33,670 square meters. Informer, reporting the same day, describes a building of over 65,000 square meters across 11 floors, while earlier announcements had cited 62,000 square meters of gross floor area. The gap between the first and second figures is nearly twofold, and the available information does not make clear whether both refer to the same measure of floor area.
Capacity figures diverge in a similar way. Informer cites more than 300 beds, while earlier announcements spoke of over 280 beds spread across 154 rooms.
The deadlines split three ways:
- according to RTS, Vucic cited March and April 2027
- Informer writes that completion is expected by mid 2027
- the contractual deadline is 1,100 calendar days, which puts completion in May 2027
None of these deadlines has been denied, and the gap between the earliest and the latest runs about two months.
What is known about the money
The Tirsova 2 contract is worth 118 million euros excluding value added tax, and the total investment is also cited as 15 billion dinars. Under an agreement between Serbia and the European Union signed in March 2024, a grant of 35 million euros was approved for the construction.
Equipment is budgeted separately. At the site, Vucic estimated Tirsova would need between 30 and 40 million euros worth of equipment, while Glisic specified that part of the equipment has already been procured and that the remaining portion costs 20 to 25 million euros.
Inside the building, the first basement level is planned to house radiological diagnostics, endoscopy and a central laboratory with a genetics department, while the second basement level will hold central sterilization, a pharmacy, a kitchen and a laundry.
Visegradska Street: phase one is 60 percent done
At the Clinic for Gynecology and Obstetrics, contractors reported that about 60 percent of phase one work is complete and that this phase could be finished by the end of October. The official announcement from the visit was more cautious: phase one by the end of the year, phase two by March 2028.
Vucic said he had been promised that all the work could be finished by the end of 2027 and called that deadline fantastic. The renovation contract was signed in July of the previous year, and it marks the first major reconstruction of the clinic in 63 years. At least 20 million euros has been announced for equipment.
The same visit brought an announcement that preventive checkups for residents over 40 will begin on September 1, and that routine checkups for children are being reinstated.
The first point where these announcements can be tested will come soon. If phase one on Visegradska Street is finished by the end of October, as contractors claim, the end of year deadline will be met with room to spare. If not, the timeline for phase two shifts toward March 2028, and the discrepancies in the Tirsova 2 deadlines will not get a real test until spring 2027.